JRMFERLAES (ROBG-458)
“Joint risk management for efficient reactions of the local authorities in the emergency situations”
What’s the goal?
The main objective of the project is to improve the common risk management in the cross-border area covered by the two municipalities: Călărași and Belene.
What’s the budget?
987,468.06 euro, din care 839,347.84 euro FEDR
Who is doing it?
Beneficiar Lider (BL): Municipalitatea Belene (Bulgaria)
Beneficiar 2 (B2): Municipalitatea Călărași (România)
When is it happening?
Start date: 15.09.2018
End date: 14.03.2021
Duration: 30 months
Where is it happening?
Pleven (Bulgaria)
Calarasi (Romania)
How is it going to happen?
- Preparation of the workshop "Best practices in crisis prevention in the cross-border region";
- Development of an online platform to provide information for crisis prevention and management;
- Creating the risk management capacity in Belene and Călărași.
What will be the results (what’s the contribution to the Programme)?
Program achievements: 82,891 people benefiting from risk management actions, flood protection measures and forest fire protection measures, 1 joint partnership in the field of joint rapid prevention and emergency response
Program results: Improving the quality of joint risk management in the cross-border area
Project status
The project obtained the following results:
Both project partners purchased during the implementation period of the project the necessary equipment for dealing with emergency situations caused by fires, natural disasters, accidents and floods:
Belene Municipality
- 1 Work platform;
- 1 Backhoe loader;
– 3 phase diesel aggregate AKSA;
- 1 Drone with camera;
– 5 Motor;
– 1 Garbage Transportation Machine;
– 5 Manual snow removal machine;
- 1 Tractor with trailer;
– 5 Motor Brush cutters.
Calarasi Municipality
– 1 Work platform;
- 3 Bobcats;
- 1 Frontal loader;
- 2 Snow removal vehicles;
- 1 Water removal vehicle.
A joint partnership agreement between Belene Municipality and Calarasi Municipality was drafted in Belene during the workshop held in the period 28-29.08.2019 and signed by the mayors on 05.12.2019. The partnership concluded between both project partners does not include actions and procedures for collaboration in the field of “early warning and joint intervention” during the sustainability period.
The online platform (https://sos-robg.eu/) for providing information for crisis prevention and management - fires, natural disasters, accidents and floods has been implemented and is populated by the two municipalities, Belene and Calarasi.
The workshop "Best practices in crisis prevention in the cross-border region" was organized in Belene.
Financial status:
According to the information available in the system, after the project implementation period ended, the progress of the project towards its financial objectives is:
• LB requested from FLC the amount of 497,186.49 euro, out of which FLC certified the amount of 382,245.97 euro, representing 76.18% from LB’s total partner budget of 501,778.87 euro.
• B2 requested from FLC the amount of 468,884.31 euro, out of which FLC certified the amount of 349,489.96 euro representing 71.96% from LB’s total partner budget of 485,689.19 euro.
Considering the amounts certified by FLC, the financial execution for the project is 74.10% from the total project’s budget of 987,468.06 euro having certified expenditures for the total amount of 731,735.93 euro.