W-TEN (ROBG-440)

Well connected nodes Giurgiu - Borovo to TEN-T transport network

What’s the goal?

The common challenge approached by the project is to improve the accessibility and mobility to the TEN-T network and thus to create suitable conditions for sustainable development in the border area.

What’s the budget?

4,945,538.25 euro, out of which 4,203,707.51 euro ERDF

Who is doing it?

Lead Beneficiary (LB): TAU Giurgiu County

Beneficiary 2 (B2): Borovo Municipality

When is it happening?

Start date: 01.08.2019

End date: 31.12.2023

Duration: 53 months

Where is it happening?

Ruse (Bulgaria)

Giurgiu (Romania)

How is it going to happen?

  • Integrated information and awareness system
  • Joint traffic management system and awareness
  • Modernization of DJ 601: Bolintin Vale – Malu Spart
  • Works in Borovo Municipality

What will be the results (what’s the contribution to the Programme)?

Programme outputs: - Modernized transport infrastructure providing access to the TEN-T network (Total length of reconstructed or upgraded roads 11.73 km.);

- 2 joint mechanisms to facilitate the connection of secondary/tertiary nodes to TEN-T infrastructure

Programme results: Cross border population served by modernized infrastructure leading to TEN-T – more than 20,877 inhabitants.

Project status

Current Project Status:

The implementation period of the project ended on 31.12.2023, but because of delays registered in the investment activity of LB, the project was included on the list of un-finalized projects. The new completion date of the project is 31.08.2024.

B2 has finalized the construction works for the modernization of 4.32 km from the street network in Borovo on 14.12.2021.

LB finalized the construction works for the modernization of 7.41 km of road in Giurgiu within the investment activity „Modernization of DJ 601: Bolintin Vale – Malu Spart DN61, km 13+685 – km 14+184 and km 22+263 – km 29+221, 7.45 km” on 23.05.2024. The reception at the finalization of the works took place on 10.07.2024.

B2 had elaborated the study „New opportunities for traffic management and traffic safety measures in Giurgiu-Borovo area”. The study examined the state of transport infrastructure in the cross-border region, identified affected areas, made a SWOT analysis of the current situation, a risk analysis related to optimizing transport conditions in the cross-border region Borovo - Giurgiu, review of applicable regulations in Bulgaria and Romania defining the institutional responsibilities of the authorities regarding transport conditions and traffic safety by analyzing their role in the whole process.

The interactive map and the smartphone application are available for free on Google play and App store under the name “Borovo Blackspots”. The map is available in Bulgarian, English and Romanian and it contains the locations of the black spots https://w-ten.info/?ait-items=blackspot-locations&lang=en.

The application allows a user to report a new accident and it also promotes important touristic objectives, which can be visited by potential tourists coming to the area and it promotes the rules of traffic safety.

B2 elaborated the Traffic Management Plan and purchased equipment on his behalf for the traffic monitoring system in order to realize a functional information system for traffic monitoring. In addition, LB purchased equipment for the traffic management system and put it onto operation on 23.11.2023. The Joint traffic management system developed by the project’s beneficiaries is functional and can be accessed at https://wtentraffic.eu/.

Within the project were organized the following events:

- 2 Conferences “New opportunities for traffic management and traffic safety measures in Giurgiu-Borovo”, one in Borovo on 24.11.2023 and one in Giurgiu on 27.11.2023.

- The Workshop „How to improve the traffic safety measures within the Giurgiu - Borovo cross-border area?” on 24.11.2023 in Borovo.

- The closing press conference on behalf of B2 took place on 11.12.2023 on Borovo with 50 participants.

- B2 implemented also the traffic awareness activities and developed the promotional materials (leaflets, posters).

Pictures

News

08 July 2024
November 2024
Mo Tu We Th Fr Sa Su
28 29 30 31 1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30 1

The content of this website does not necessarily represent the official position of the European Union. The initiators of the site are the sole responsible for the information provided through the site.