SEVEN-T (ROBG- 432)

Silistra – Ecofriendly – Viable – Electrical – Navodari Transport

What’s the goal?

To improve tertiary nodes connection by reconstruction of 4,315 m of road and introducing eco-friendly-transportation in the Silistra - Navodari cross-border area.

What’s the budget?

7.896.727,79 euro, out of which 6,712,218.61 euro ERDF

Who is doing it?

Lead Beneficiary (LB): Territorial Administrative Unit - Navodari Town (Romania)

Beneficiary 2 (B2): Silistra Municipality (Bulgaria)

When is it happening?

Start date: 24.04.2018

End date: 23.03.2023

Duration: 49 months

Where is it happening?

Constanta in Romania

Silistra in Bulgaria

How is it going to happen?

  • Elaboration of a Joint Strategy whose aim will be to identify better transport services for the citizens in the cross-border area, improve the accessibility and mobility of people with minimum effects on the environment and propose future projects to be developed in common;
  • Elaboration of a Joint Route Guide which will gather information about bicycle lanes and routes, sightseeing - cultural and natural heritage, hotels, shops and garages for bicycles in the region of Silistra and Navodari;
  • Construction of a 14.414 m of bike lanes, construction of 7 bike docks in Silistra (for standard and electric bikes), 36 bus and bike stations in Navodari and 1 solar parking in Silistra;
  • Rehabilitation of 4.315 km of road;
  • Organization of communication and promotion activities.

What will be the results (what’s the contribution to the Programme)?

Programme outputs: 

4,315 km of rehabilitated roads;

2 joint mechanisms that facilitate the connection of secondary/tertiary nodes to TEN-T infrastructure;

Programme results

68,211 persons from the cross border area will be served by modernized infrastructure leading to TEN-T

Project status

The Project is in the 48th month of implementation out of 60 months. The physical progress, is as follows:

LB has completed the works for bike lanes in Navodari and the amount of traffic signs and poles according to the works report no.16/25.08.2021.

Beneficiary 2 - On 18th September 2020 were selected the contractors under the 2 lots. Contract N 2020-C-018 from 29.10.2020 with Kreal 21 LTD for construction of Solar parking and Contract N 2020-C-017 from 29.10.2020 with ATD Group LTD for construction of bike lines. On 21th April 2021 made record for the opening of a construction site and determining of construction line and level and made advance payment regarding the contract – 30 % from the amount of the contract. In that period the construction works is going regarding the technical offer.

On 5th July 2021 was selected the contractor under procurement procedure for delivery of docks and standard and electric bicycle -

LB competed the Navodari Boulevard rehabilitation according to the Work reports no.15 and 16, but do not have the final reception.

45 road signs - traffic signs together with poles have been mounted according Works report no.16/25.08.2021.

In regards to the 36 bus stations and the related equipment, 7 bus stations were relocated as follow:

1 bus station from Albinelor street, 1 bus station from Constantei street and 2 bus stations from Plopilor street was placed on Navodari Boulevard. Also, another 3 bus stations were relocated from Randunelelor street to Navodari Boulevard, sector from Gate-Black Sea Canal towards Lumina.

B2 - finished the Vaptsarov street rehabilitation with Certificate 15 from 28th February 2020 issued by the bodies of the Directorate for national construction control, under the conditions and by the order of, determined in an ordinance by the Minister of Investment Project Development.

1 videoclip related to the main investment have been elaborated in the current reporting period and have been uploaded on project website and on youtube. Until the present moment 9 video clips have been elaborated and uploaded on the project website, regarding the contract no. 16240/18.02.2020, signed between the City Hall of Navodari and SC YOUART VISION SRL.The video clips can be access on the links below:

https://youtu.be/prRoMPYbmO8

https://youtu.be/3XKHrxoMsqc

https://youtu.be/6thV5sAeCcs

https://youtu.be/VBt9p8-RQHk

https://youtu.be/p4KuQ_syBi4

https://youtu.be/7_T6dImmA18

https://youtu.be/NoFvrZiXJt4

https://youtu.be/WKpGpYU-V-A

https://youtu.be/0k3mKjJHupw

The project website is updated and functional, and could be accessed here: https://ro.seven-t.ro/.

Pictures

June 2023
Mo Tu We Th Fr Sa Su
29 30 31 1 2 3 4
5 6 7 8 9 10 11
12 13 14 15 16 17 18
19 20 21 22 23 24 25
26 27 28 29 30 1 2

The content of this website does not necessarily represent the official position of the European Union. The initiators of the site are the sole responsible for the information provided through the site.