STD (ROBG-138)

The streamline of the traffic in the cross border Danubian area

What’s the goal?

To improve the planning, development and coordination of cross border transport systems for better connections to TEN-T transport network.

What’s the budget?

7,943,701.93 euro, out of which 6,752,146.63 ERDF

Who’s doing it?

Lead beneficiary (LB): Territorial Administrative Unit - Mehedinti County (Romania)

Beneficiary 2 (B2): Dolna Mitropolia Municipality (Bulgaria)

When is it happening?

Start date: 12.12.2017

End date: 11.12.2023

Duration: 72 months

Where is it happening?

Cerneti, Dedovita Noua, Dedovita Veche, Valea Copcii, Dudasu, Alunisu, Baditesti, Husnicioara, Borogea, Celnata, Dumbravita, Marmanu, Opranesti, Peri, Priboiesti, Selisteni, Prunisor, Balota, Cervenita, Lumnic, Zegaia, Paltinisu, Govodarva, Rosia, Negresti, Mehedinti County, Romania

Dolna Mitropolia, Podem, Riben, Bozhurets, Pobeda and Bivolare, Dolna Mitropolia Municipality,Pleven District, Bulgaria

How’s it going to happen?

  • 27,38 km modernized on the Romanian territory - modernization DJ607A – Ringroad Drobeta - TurnuSeverin–Cerneti – ValeaCopcii – Peri – Prunisor (E70-TEN-T);
  • 6,450 km modernized on the Bulgarian territory - rehabilitation of road PVN1041, road PVN2046 and road PVN3044;
  • Organizing 3 press conferences and 8 press releases (4 in Romania, 4 in Bulgaria);
  • Information and publicity materials (temporary and permanent billboards);

What will be the results (what’s the contribution to the Programme)?

Programme outputs:

- 33,83 km total length of reconstructed or upgraded roads

Programme results: Cross border population (535,142 people: Pleven District = 269,752 persons and Mehedinti County = 265,390 persons) served by modernized infrastructure leading to TEN-T

Project status:

Considering that the project envisages road rehabilitation, the main progress registered at project level consists of the actions implemented by both project partners so far, as detailed below:

LB updated the feasibility study and launched for the third time the public procurement procedure for design and works for modernization of 27.819 km of roads (DJ607A – Ringroad Drobeta – TurnuSeverin–Cerneti – ValeaCopcii – Peri – Prunisor -E70-TEN-T), in September 2019. Following the evaluation process of the three offers received, an execution contract was signed in January 2020, expected to be finalized until July 2022. The physical stage of the works has reached 17% so far, representing the execution of tubular bridges, dalat bridges, docking boxes, cassette execution and execution of broken stone foundation at the abutments. In addition, during the present reporting period, LB reported also the acquisition, respectively installation and placement of the 8 temporary panels among the investment objective.

B2 succeeded to assess the submitted offers and awarded three distinct contracts (for each of the three sections - road PVN1041, road PVN2046 and road PVN3044, a different contract was signed). Following the signed contracts, the construction sites of all three Lots of the investment were opened at the end of November 2019. So far, the execution of the works part from investment objective 2 – „Rehabilitation of Municipal road network of PVN 2046 / ІІІ-118, Podem – Dolna Mitropolia / - Bivolare/ PVN 1042”,Km 0+00 – Km 1+800” and investment objective 3 -„Rehabilitation of Municipal road network of PVN 3044 / ІІІ-118, Podem – Dolna Mitropolia / - Bozhuritsa / PVN 1042, from Km 0+000 to Km 2+100” were finalized since the beginning of June 2020. The construction works, which are part from investment objective 1 - „Rehabilitation of Municipal road network of PVN 1041/ ІІІ-118, Komarevo - Dolna Mitropolia / - Podem - Riben - DZS 1 MAY from Km 0 + 750 to Km 3 + 300“ were also finalized. The Permit for acceptance and use is issued from Directorate for National Construction Control for Road acceptance in the beginning of August 2020. The complete rehabilitation of road PVN1041, road PVN2046 and road PVN3044 is representing a length from 6.45 km rehabilitated road sections modernized on the Bulgarian territory.

Pictures

May 2021
Mo Tu We Th Fr Sa Su
26 27 28 29 30 1 2
3 4 5 6 7 8 9
10 11 12 13 14 15 16
17 18 19 20 21 22 23
24 25 26 27 28 29 30
31 1 2 3 4 5 6

The content of this website does not necessarily represent the official position of the European Union. The initiators of the site are the sole responsible for the information provided through the site.