MN-DJ: CLOSER (ROBG-390)

Montana – Dolj : Better access-closer communities

What’s the goal?

The development of the area by improving access between nodes and the TEN-T network in the region. The proposed project envisages the modernization of two roads - Road II-81 Kostinbrod-Berkovitsa-Montana from km 94 + 000 to km 101 + 199.48, Montana district and road DJ561B Segarcea-Drănic from km 0 + 000 to km 12 + 130, county Dolj with a total length of 19.32 km.

What’s the budget?

7,737,783.80 euros, of which 6,577 116.22 euros ERDF

The deadline for the half of the project implementation period is October 31, 2021.

BL: the target at the middle of the implementation period assumed in the financing contract is 5,230 euros;

B2: the target at the middle of the implementation period assumed in the financing contract is 7,034 euros.

Who is doing it?

Lead Beneficiary (LB): Road Infrastructure Agency Bulgaria

Beneficiary 2 (B2): Territorial Administrativ Unit Dolj County (Romania)

When is it happening?

Start date: 02.04.2020

End date: 29.03.2023

Duration: 35 months and 28 days.

Where is it happening?

Montana in Bulgaria

Dolj in Romania

How is it going to happen?

  • Modernization of the DJ561B Segarcea-Drănic road from km 0 + 000 to km 12 + 130, Dolj county;
  • Modernization of the II-81 Kostinbrod-Berkovitsa-Montana road from km 94 + 000 to km 101 + 199.48, Montana district;
  • Development of 5 common mechanisms consisting of education and information campaigns (awareness);
  • Organizing communication and promotion activities.

What will be the results (what’s the contribution to the Programme)?

Program achievements: 19.32 km of rehabilitated roads, 3 common mechanisms that facilitate the connection of secondary / tertiary nodes to the TEN-T infrastructure

The results of the program: 67,177 people from the cross-border area will be served by modernized infrastructure leading to TEN-T

Project status

The project is currently in the 27th month of implementation period.

During the reported period, the beneficiaries of the project focused on the infrastructure activities.

Regarding the investment I1 "Modernization of the II-81 road" in Montana, Lead Beneficiary concluded on 14.08.2020 the contract for construction works and on 21.07.2020 the contract for works supervision services.

The construction permit was issued on 09.06.2020, and the start date of the construction works was 24.09.2020. From 29.11.2021, the works are completed, following the signing of Protocol 16 in accordance with the requirements of the Law on Spatial Planning and the construction to be put into operation.

On 17.12.2020, LB concluded a contract for the distribution of materials provided for in Activity T1 - “Common traffic safety measures”. All services were provided and promotional materials were delivered. The protocol for providing the service performed was signed on 05.02.2021;

On behalf of B2, a contract for the delivery of all deliverables included in Activity A.T1.1 “Child safety education” as well as in Activity A.T1.2 “Adult awareness campaign for speed management and human tolerance on roads ”Was concluded on 30.09.2020. This contract will also provide all deliverables for the "Communication" work package.

For the investment I2 “Modernization of the county road DJ 561B”, B2 the technical design was elaborated according to the contract no. 02/11.01.2021, and the public procurement procedure for the works contract was launched on 31.03.2022.

Pictures

July 2022
Mo Tu We Th Fr Sa Su
27 28 29 30 1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30 31

The content of this website does not necessarily represent the official position of the European Union. The initiators of the site are the sole responsible for the information provided through the site.