MEDDOB (ROBG–439)
“Improving the connection to the TEN-T network in the cross-border area Medgidia - Dobrich”
What’s the goal?
To ensure better traffic conditions for the population of the 2 cities, as well as for the other traffic participants who are transiting. |
What’s the budget?
7,988,762.56 euro, out of which 6,790,448.17 euro ERDF
Who is doing it?
Lead Beneficiary (LB): TAU Medgidia Municipality (Romania)
Beneficiary 2 (B2): Dobrich Municipality (Bulgaria)
When is it happening?
Start date: 24.04.2018
End date: 23.12.2021
Duration: 44 months
Where is it happening?
Medgidia in Romania
Dobrich in Bulgaria
How is it going to happen?
|
What will be the results (what’s the contribution to the Programme)?
Programme outputs: 3 joint mechanisms to facilitate the connection of secondary/tertiary nodes to TEN-T infrastructure; 13.73 km of reconstructed or upgraded roads
Programme results: 136,114 Cross border population served by modernized infrastructure leading to TEN-T
Project status
The project is finalized. The Final Implementation Report has to be submit until 23rd of May 2022.
The reported achievements so far are as follows:
- Finalizing the upgrading of 13,73 km of road infrastructure in order to connect secondary (Dobrich) and tertiary (Medgidia) nodes to TEN-T infrastructure and to reduce transportation time and optimizing logistics. 6,104 km of roads was modernized through this investment in Medgidia and 7,632 km of roads was modernized through this investment in Dobrich
- LB finalized the acquisition of the two mechanism - Route Guidance and Safety measures, which were delivered on 15.10.2021.
- LB finalized the acquisition for the two-maintenance equipment: Backhoe with accessories and High-pressure machine for unclogging the small bridges, gutters, ditches, etc. The machines were delivered on 19.07.2021, respectively 30.06.2021.
- B2 signed the acquisition contracts of the three mechanism - Route Guidance, Safety measures and Awareness raising activities in schools.